Substation approval from the Chief Electric Inspector (OCEI)

A new substation needs approval from the Office of the Chief Electric Inspector (OCEI) before it is energised. The OCEI runs an e-service portal for substation approvals, contractor licences and electrician licences.

Two engineers reviewing a single-line diagram on a construction site table
Illustrative image

Who files the application

The owner is the applicant. A licensed contractor normally prepares the drawings and documents and files them with the owner's papers. We do this for every substation we build, and we confirm the current process at survey.

Steps

  1. 1

    Design

    Load list, single-line diagram and room layout prepared by the licensed contractor.

  2. 2

    Application

    Application with drawings and documents submitted through the OCEI e-service portal.

  3. 3

    Review

    OCEI reviews the drawings and may ask for changes.

  4. 4

    Installation

    Equipment is installed to the approved drawing.

  5. 5

    Inspection

    Inspection and test reports before the supply is switched on.

  6. 6

    Utility connection

    The utility completes its own process and energises the supply.

Frequently asked questions

Who applies for substation approval: the owner or the contractor?

The owner is the applicant. The licensed contractor usually prepares the drawings and documents and files them with the owner's papers. We do this for you.

How long does OCEI approval take?

It depends on how complete the file is and on inspection scheduling. A complete, correct file avoids most delays.

Can a substation be energised before approval?

No. Inspection and approval come before the supply is switched on.